An Exciting New Chapter: Gas-N-Wash Tinley Park

At 4 p.m. on August 28th, 2024, I received the call for my next assignment:

“Mike, your next chapter starts tomorrow. Be at the Gas N Wash Tinley Park project by 6:00 a.m. tomorrow to shadow Matt Lux. You’ll be learning, helping, and working on-site for the next few months until the project is complete!”

Excited was an understatement. This wasn’t just any project-it was one of the largest and most complex undertakings our company had at the time. It was a 6.3 acre, new to industry Gas Station and Car Wash, with complex retaining walls, several ground-up buildings, massive canopies, and drastic changes in elevation. All of it to be done under an increasingly tight timeline.

Before starting the Gas N Wash project, I had wrapped up a much smaller job: a YMCA remodel in Chicago. While that project was more compact, the goal was the same-stay ahead of the subcontractors and focus on the end goal. “Deliver successful turnover by the project due date.” With the Gas N Wash project, however, the stakes felt much higher.


Boots on the Ground

From my first day on the job, the site was bustling with activity, and the number of subcontractors was overwhelming. I remember looking around in awe, wondering, “How does one manage and direct all of this?” This was just the beginning.

Over the first few days, my task was simple: observe, ask questions, and learn. Our rule was that there are no dumb questions, and I embraced that wholeheartedly. I made it a point to introduce myself to the subcontractors. When possible, I would catch them during their breaks to have a quick chat and break the ice. I quickly learned that everyone was not only approachable, but eager to teach. Our site superintendent, Matt, a company veteran, told me, “If you don’t learn something new every day, you’re not trying hard enough.” That mantra stuck with me throughout the entire project.

When I first arrived, the convenience store’s exterior shell was nearly complete. The masonry walls were up and the metal roof decking was in place. There was still a lot of work to do. The interior framing had just started, windows were nonexistent, and MEP (mechanical, electrical, and plumbing) systems were just beginning.

The car wash, on the other hand, was still in its early stages. The masonry block walls were being laid. The main retaining wall along LaGrange Road was in the process of being formed and poured. Both canopies had their piers poured, but the red iron structure hadn’t been delivered yet. And the site work? Still a long way from complete, with dirt and stone covering much of the ground.



Breaking the Project Into Milestones

To keep things moving, we divided the project into individual “mini-projects,” each playing a vital role in the project’s critical path. At this stage, the western most retaining wall was our top priority. Weather, as always, was our biggest challenge. We worked tirelessly to keep the concrete crew moving, pumping water out of the excavations and moving materials when necessary.

Why was this retaining wall so crucial? Once completed, it would make room for the installation of the underground storage tanks (USTs)-a major milestone and key component of the fuel systems. With the USTs in place, we could proceed with backfilling and continue with underground piping and electrical work for the fuel dispensers. Only then could we move forward with erecting the canopy. It was a textbook example of how one step leads to another, and how each task directly affects the project’s critical path.




A Site In Motion

While all of this was happening, the convenience store and car wash were in constant motion. Subcontractors worked tirelessly on framing, drywall, tiling, and painting the interior of the store. Meanwhile, Matt and I were busy doing some survey work, laying out curbs for the concrete crew, while the excavation subcontractor continued grading and moving dirt across the site. The car wash subcontractors were working on masonry walls, flexi-core roofing, and MEP installations, while also preparing for the arrival of carwash equipment.




Months of Learning and Growth

Over the next five months, I spent nearly every day on-site. I learned the ins and outs of building a gas station-and a car wash-everything from the smallest details in the blueprints, such as stop sign height, to the numerous inspections that took place for MEPs, fire safety, framing, and fuel tank installations. I learned how to coordinate multiple subs working in the same area, how to collaborate with tenants, and how to juggle competing demands across the site. Each day brought new challenges and learning opportunities, all leading to the grand opening.

The Final Push

The final weeks flew by as we raced toward the finish line. Landscaping was installed, electronics for the pumps were tested, and safety checks-especially for the OSFM (Office of Illinois State Fire Marshal) inspection-were completed. We installed signage throughout the site, ensuring both vehicular traffic flow and visibility for advertising. It was exciting to watch as gas station vendors filled the store with their products and tenants began testing out their food and drinks-one of the most enjoyable perks of the job!

We wrapped up final touches like paint and caulking, and before we knew it, opening day was upon us. The anticipation was palpable, and while there’s always a bit of nervousness hoping everything works as planned, it was exhilarating to see it all come together.

The Grand Opening

The opening day was a success-no issues, no hiccups. The lot was flooded with eager customers filling up with fuel, washing their cars, and enjoying the delicious food from Orland Park Bakery and Heinie’s McCarthy’s Chicken. It was rewarding to see all the hard work come to fruition and to witness the site buzzing with life.





Written by: Mike Milani – Assistant Construction Manager